Analisis Faktor Penyebab Time Overrun Proyek Pembangkit Listrik Dengan Pendekatan Partial Least Square Structural Equation Modeling
Abstract
Power plant projects are crucial to providing andining a reliable power system. Power plant projects, like other construction projects, often experience a problem of delayed completion of work known as time overrun, which can result in financial losses and project failure to be completed on time. Time overrun is overtime that exceeds the completion date specified in the contract or the project submission date agreed by both parties. Engineering, procurement, construction, and commissioning are all parts of the power plant construction project. In completing the project, it is essential to understand why the power plant construction project is delayed and how to properly mitigate the risk. This research is quantitative research, which means using a questionnaire. The aim of this study is to find out what caused the time overrun of the power plant project at the Timorese PLTU. Partial Least Square Structural Equation Modeling (PLS-SEM) is used to process data from questionnaire results. The results of the research showed that there were seven research hypotheses, with two accepted and five rejected. The external factors, and the owner-related factors are the time overrun factors based on the accepted hypothesis. Based on the cause of the time overrun, some mitigation measures can be recommended to management including a memorandum of understanding (MoU) scheme with stakeholders related to existing permits, a scheme related to contractual and technical procedures when unforeseen conditions occur and ensuring the quality of the results of the soil investigation.
Keywords
Full Text:
PDF (Bahasa Indonesia)References
Akhund, M. A., Imad, H. U., Memon, N. A., Siddiqui, F. H., Khoso, A. R., & Panhwar, A. A. (2018). Contributing Factors of Time Overrun in Public Sector Construction Projects. In Technology & Applied Science Research (Vol. 8, Issue 5). www.etasr.com
Al-Hazim, N., Salem, Z. A., & Ahmad, H. (2017). Delay and Cost Overrun in Infrastructure Projects in Jordan. Procedia Engineering, 182, 18–24. https://doi.org/10.1016/j.proeng.2017.03.105
Aljarallah, N., Alsugair, A. M., Almohsen, A., & Al-Gahtani, K. (2024). Identifying the significant causes of waste of housing infrastructure projects in the Kingdom of Saudi Arabia. Alexandria Engineering Journal, 86, 217–229. https://doi.org/10.1016/j.aej.2023.11.063
Alrasheed, K., Soliman, E., & Albader, H. (2023). Systematic review of construction project delays in Kuwait. Journal of Engineering Research, 11, 347–355. https://doi.org/10.1016/j.jer.2023.08.009
Alsuliman, J. A. (2019). Causes of delay in Saudi public construction projects. Alexandria Engineering Journal, 58(2), 801–808. https://doi.org/10.1016/j.aej.2019.07.002
Chandragiri, A. B., Jeelani, S. H., Akthar, S., & Lingeshwaran, N. (2021). A study and identification of the time and cost overrun in the construction project. Materials Today: Proceedings, 47, 5426–5431. https://doi.org/10.1016/j.matpr.2021.06.268
Cheah, J.-H., Chuah, F., & Ting, H. (2017). PLS-SEM using SmartPLS 3.0: Chapter 13: Assessment of Moderation Analysis. https://www.researchgate.net/publication/341357609
Daoud, A. O., El Hefnawy, M., & Wefki, H. (2023). Investigation of critical factors affecting cost overruns and delays in Egyptian megaconstruction projects. Alexandria Engineering Journal, 83, 326–334. https://doi.org/10.1016/j.aej.2023.10.052
Fauzy, A. (2019). Metode Sampling. Universitas Terbuka. www.ut.ac.id.
Giri, O. P. (2023). Perception-Based Assessment of the Factors Causing Delays in Construction Projects. Engineering, 15(07), 431–445. https://doi.org/10.4236/eng.2023.157033
Hair, J. F., Black, W. C., Babin, B. J., & Anderson, R. E. (2019). Multivariate Data Analysis Eighth Edition. www.cengage.com/highered
Hair, J. F., Sarstedt, M., Hopkins, L., & Kuppelwieser, V. G. (2014). Partial least squares structural equation modeling (PLS-SEM): An emerging tool in business research. In European Business Review (Vol. 26, Issue 2, pp. 106–121). Emerald Group Publishing Ltd. https://doi.org/10.1108/EBR-10-2013-0128
Hari, P., & Pandey, M. (2016). Causes Of The Time Delay In Construction Housing Projects In Gwalior Division. International Research Journal of Engineering and Technology, 03(12). www.irjet.net
Hossan, D., Aktar, A., & Zhang, Q. (2024). A Study On Partial Least Squares Structural Equation Modeling (Pls-Sem) As Emerging Tool In Action Research Lc International Journal Of Stem A Study On Partial Least Squares Structural Equation Modeling (Pls-Sem) As Emerging Tool In Action Research. 01(04). https://www.researchgate.net/publication/348732775
Hair, J. F., Hult, G. T., Ringle. Christian M, & Sarstedt, M. (2017). A Primer on Partial Least Squares Structural Equation Modeling (PLS-SEM) Second Edition.
Kautsarina, Hidayanto, A. N., Anggorojati, B., Abidin, Z., & Phusavat, K. (2020). Data modeling positive security behavior implementation among smart device users in Indonesia: A partial least squares structural equation modeling approach (PLS-SEM). Data in Brief, 30. https://doi.org/10.1016/j.dib.2020.105588
Larson, E. W., & Gray, C. F. (2011). Project management : the managerial process (Fifth). McGraw-Hill.
Memon, A. H., Memon, A. Q., Khahro, S. H., & Javed, Y. (2023). Investigation of Project Delays: Towards a Sustainable Construction Industry. Sustainability (Switzerland), 15(2). https://doi.org/10.3390/su15021457
Rahadi, D. R. (2023). Pengantar Partial Least Squares Structural Equation Modeling (PLS-SEM). CV. Lentera Ilmu Madani.
Sarstedt, M., Ringle, C. M., & Hair, J. F. (2021). Partial Least Squares Structural Equation Modeling. In Handbook of Market Research (pp. 1–47). Springer International Publishing. https://doi.org/10.1007/978-3-319-05542-8_15-2
Sugiyono. (2013). Metode Penelitian Kuantitatif, Kualitatif dan R&D. CV. Alfabeta.
Al Maktoumi, I. S., Khan, F. R., & Al Maktoumi, A. R. S. (2020). Assessing the Factors Causing Project Completion Delays in the Construction Sector of Oman using SEM-PLS. Humanities & Social Sciences Reviews, 8(3), 900–912. https://doi.org/10.18510/hssr.2020.8394
Tariq, J., & Gardezi, S. S. S. (2022). Study the delays and conflicts for construction projects and their mutual relationship: A review. Ain Shams Engineering Journal, 14. https://doi.org/10.1016/j.asej.2022.101815
Tawfek, A. M., & Bera, D. K. (2018). Delay in Construction Projects: Types, Causes and Effects. https://www.researchgate.net/publication/365322620
Yana, A. A. G. A., Rusdhi, H. A., & Wibowo, M. A. (2015). Analysis of factors affecting design changes in construction project with Partial Least Square (PLS). Procedia Engineering, 125, 40–45. https://doi.org/10.1016/j.proeng.2015.11.007
Yap, J. B. H., Goay, P. L., Woon, Y. B., & Skitmore, M. (2021). Revisiting critical delay factors for construction: Analysing projects in Malaysia. Alexandria Engineering Journal, 60(1), 1717–1729. https://doi.org/10.1016/j.aej.2020.11.021
DOI
https://doi.org/10.21107/rekayasa.v17i2.26597Metrics
Refbacks
- There are currently no refbacks.
Copyright (c) 2024 Haryo Dwito Armono, Agus Dwi Ariyanto
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.