Analisis Waktu dan Biaya Penyelesaian Proyek Transmisi 150 kV Dengan Pendekatan Critical Path Method dan Time Cost Trade Off

Muhamad Eriq Ashari, Haryo Dwito Armono

Abstract

The construction of the 150 kV Transmission electricity infrastructure by PT PLN (Persero) is an assignment from the Government in order to support electricity growth in Indonesia. Several 150 kV Transmission projects experienced delays in project completion due to inaccurate timing and project completion costs. The construction project of the 150 kV transmission involves engineering, procurement, construction, and commissioning activities, requiring careful calculations of time and costs while considering resources (Man, Material, Machine, and Method). The Critical Path Method (CPM) is used as the deterministic analysis approach for time analysis, while the Time Cost Trade-Off (TCTO) method is employed when there is a potential for project delays, acceleration, or cost overrun. The combination of the CPM and TCTO methods is suitable for project activities that are precisely known, while considering both parallel and serial work. Based on the research results, the 150 kV transmission project has 13 critical paths. The acceleration scheme that significantly impacts time and cost is the acceleration during the construction phase, and changes in all resource variables (Man, Material, Machine, and Method) affect both time and cost. However, a change in a single resource variable, namely Method, may impact time but not necessarily cost.

Keywords

infrastructure, electricity, resources, critical path

References

Amat Pawiro, D., Suharyanto, & Atmojo, P. S. (2015). Optimasi Biaya dan Waktu dalam Penyusunan Jadwal Pelaksanaan Proyek (Studi Kasus Proyek Pembangunan Gedung Pusat Kegiatan Mahasiswa Universitas Diponegoro Semarang). Media Komunikasi Teknik Sipil, 20(2), 103–108. https://doi.org/10.12777/mkts.20.2.103-108

Aslimeri, Ganefri, & Hamdi, Z. (2008). Teknik Transmisi Tenaga Listrik. Departemen Pendidikan Nasional.

Bindu, P. H. (2015). Approach of Crashing Critical Activity ( CCA ) and Stretching Non-critical Activities ( SNA ) of Time Cost Trade off problems using Critical Path Method. 5(2), 1–10.

Budianto, E. A., & Husin, A. E. (2021). Analisis Optimasi Waktu dan Biaya Dengan Metode Time Cost Trade Off pada Proyek Gudang Amunisi. In Jurnal Aplikasi Teknik Sipil (Vol. 19, Nomor 3).

Ervianto, & Wulfram, I. (2002). Manajemen Proyek Konstruksi (Edisi Pert). Salemba Empat.

Ervianto, & Wulfram, I. (2004). Teori Aplikasi Manajemen Proyek Konstruksi. Salemba Empat.

Gray, C. F., Larson, E. W., & Desai, G. V. (2011). Project Management The Managerials Process (6th ed.). Mc Graw Hill Education.

Haga, W. A., & Marold, K. A. (2004). A Simulation Approach To The PERT/CPM Time-Cost Trade-Off Problem. June.

Handayani, A., & Khoerul, D. (2020). Time Cost Trade Off Analysis on the Trainning Center Project PT. X With Additional Working Hours. International Journal of Engineering and Natural Science, 6(1), 38–46. http://adri.journal.or.id/index.php/ijens/index

Harjanto, R., Azis, S., & Hidayat, S. (2019). The accelerating of duration and change of cost on construction project implementation. International Journal of Civil Engineering and Technology, 10(1), 825–832.

Heizer, J., & Render, B. (2001). Prinsip-Prinsip Manajemen Operasi. Salemba Empat.

Heizer, J., & Render, B. (2008). Operations Management. Salemba Empat.

Heizer, J., & Render, B. (2014). Manajemen Operasi (S. Empat (Ed.)).

Herdianti, W. A. (2016). Perencanaan Proyek Pipa Transmisi Gas Gresik-Semarang. https://repository.its.ac.id/1428/

Herjanto, E. (2007). Manajemen Operasi (Edisi Keti). Grasindo.

Izzah, N. (2017). Analisis Pertukaran Waktu dan Biaya Menggunakan Metode Time Cost Trade Off (TCTO) pada Proyek Pembangunan Perumahan di PT. X. 10(1), 51–58.

Kamandang, Z. R. (2020). Identification of Critical Path Changes and Concurrent Delays Using EDAM Method for Building Project. Journal of Applied Sciences, Management and Engineering Technology, 1(1), 8–13. https://doi.org/10.31284/j.jasmet.2020.v1i1.867

Khaled, E.-R., & Moselhi, O. (2001). Optimizing Resource Utilization for Repetitive Construction Projects. February, 18–27.

Laily, N., Azizah, L., Dosen, P., Silvianita, S. T., Mulyadi, E. Y., Teknik, J., Fakultas, K., & Kelautan, T. (2016). Analisa percepatan waktu pada proyek transmisi gas gresik-semarang dengan metode time cost trade off.

Metwally El-Kholy, A., Sheshtawy, A. I., Ragheb, S. R., & Mohammed, O. F. (2021). Time-Cost Trade-off in Recurring Projects Considering Interruption, Buffer, and Schedule Acceleration. International Journal of Construction Engineering and Management, 2, 31–47. https://doi.org/10.5923/j.ijcem.20211002.02

Munawaroh. (2003). Principle of Management Construction. Jendela Ilmu.

Nuciferani, F. T., Aulady, M. F. N., & Wibowo, P. A. (2019). (cetak); ISSN 2527-3892 (elektronik) Fakultas Teknik Universitas Islam Balitar, Blitar. 2019. Pengurangan Risiko Pinalti dengan Time Cost Trade Off pada Proyek Konstruksi. In Jurnal Qua Teknika (Vol. 9, Nomor 2).

Pratama, Y. A. (2020). Analisis Penjadwalan Proyek Dengan Metode PERT. Universitas Islam Indonesia.

Priyo, M., & Putra, R. H. (2021). Studi Optimasi Biaya Dan Waktu Menggunakan Metode Time Cost Trade Off Pada Proyek Pembangunan Gedung Global Sevilla School Jakarta (Studi of Cost and Time Optimization Method Using Time Cost Trade Off on Building Global Sevilla School Jakarta) (Vol. 3, Nomor 2).

Priyo, M., & Sudiro, S. (2017). Studi Optimasi Waktu dan Biaya dengan Metode Time Cost Trade Off pada Proyek Konstruksi : Studi Kasus Proyek Jalan Bugel-Galur-Poncosari Cs. Tahap I, Provinsi D.I. Yogyakarta (Cost and Time Optimization Study with Time Cost Trade Off Method on Constructio. 20(2), 172–186.

Siagian, S. P. (1998). Manajemen Sumber Daya Manusia. Bumi Aksara.

Soeharto, I. (1997). Manajemen Proyek dari Konseptual Sampai Operasional. Erlangga.

Soeharto, I. (1999). Manajemen Proyek (Dari Konseptual Sampai Operasional) (Edisi Kedu). Erlangga.

Soemardi, B.W., R.D. Wirahadikusumah, M. A. dan N. P. (2007). Konsep Earned Value untuk Pengelolaan Proyek Konstruksi. Laporan Hasil Riset, ITB. 1–13.

Vanhoucke, M., & Debels, D. (2007). The discrete time/cost trade-off problem: Extensions and heuristic procedures. Journal of Scheduling, 10(4–5), 311–326. https://doi.org/10.1007/s10951-007-0031-y

DOI

https://doi.org/10.21107/rekayasa.v16i2.20501

Metrics

Refbacks

  • There are currently no refbacks.


Copyright (c) 2023 Muhamad Eriq Ashari, Haryo Dwito Armono

Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.